PLUS Kulai-Sedenak lane widening project – road diversions for bridge beam installation work, Oct 27-30

0
16

PLUS Kulai-Sedenak lane widening project – road diversions for bridge beam installation work, Oct 27-30

PLUS has announced that a series of road diversions will be implemented along the Kulai–Sedenak stretch of the North-South expressway (NSE) from October 27 to 30 to facilitate the installation of bridge beams on the route. This is part of the lane widening project from Yong Peng to Senai northbound.

The road diversion involves two locations, namely KM34.20 to KM36.20 southbound and KM32.50 to KM34.50 northbound, between 10 pm and 5 am daily throughout the specified period. During these hours, vehicles will be diverted to the rightmost lane to create a safe work zone while minimising traffic disruption to highway users.

The highway concessionaire advised highway users to plan their journeys accordingly and use the PLUS app to obtain the latest traffic updates. Users are also reminded to adhere to all signage and instructions issued by PLUS personnel when passing through the construction areas.

The first phase of the additional lane construction project consists of two packages, namely Package A (Sedenak-Kulai) and Package B (Kulai-Senai Utara), covering a distance of 22 km. Work on the project is expected to be completed by January 2028.